Impact of Contract Change Order (CCO) on Cost and Time Performance of the Eretan Coastal Flooding (Rob) Mitigation Project, Indramayu Regency

Authors

  • Randi Adidaya Eliza Universitas PGRI Semarang Author
  • Edi Ujang Purnomo Universitas PGRI Semarang Author
  • Dr. Ir. Ibnu Toto Husodo, S.T., M.T., IPU,. ASEAN Eng Universitas PGRI Semarang Author
  • Dr. Ir. Putri Anggi Permata Suwandi, S.T., M.T. Universitas PGRI Semarang Author https://orcid.org/0000-0002-0821-2732

DOI:

https://doi.org/10.26877/ijosbie.v7i2.1282

Keywords:

contract change order, construction cost, construction schedule, critical path method, coastal flood handling

Abstract

Contract Change Order (CCO) is a formal mechanism used to accommodate changes to construction contracts during project execution. This study analyzes the causes of CCO and its impact on cost and time in the Eretan Coastal Flood (Rob) Handling Project, Indramayu Regency, where the initial concrete-cube breakwater design was revised into an L-Shape precast structure. A descriptive qualitative method with a quantitative approach was applied, using NVivo to identify causal factors from interviews and technical justification documents, and Microsoft Project with the Critical Path Method (CPM) to assess schedule impact, while cost impact was evaluated by comparing the Bill of Quantity before and after the amendment. Results show that the CCO was caused by the need to adjust the design to actual field conditions. The change altered the composition of work items significantly, yet the total contract value remained Rp18,911,932,131.39 (0% change) and project duration remained 280 calendar days (ΔT = 0), indicating the CCO was managed as a constructive, cost- and time-neutral change.

Author Biographies

  • Randi Adidaya Eliza, Universitas PGRI Semarang

    Department of Civil Engineering

  • Edi Ujang Purnomo, Universitas PGRI Semarang

    Department of Civil Engineering

  • Dr. Ir. Ibnu Toto Husodo, S.T., M.T., IPU,. ASEAN Eng, Universitas PGRI Semarang

    Department of Civil Engineering

  • Dr. Ir. Putri Anggi Permata Suwandi, S.T., M.T., Universitas PGRI Semarang

    Department of Civil Engineering

References

[1] S. I. Yunisa and V. H. Puspasari, “A Study of Factors Causing Contract Change Order (CCO) in Construction Projects in Palangka Raya City,” Jurnal Basement Teknik Sipil, vol. 2, no. 1, 2024.

[2] P. A. D. Yanti, I. G. N. Sunatha, and I. P. Y. Hermawan, “The Effect of Contract Change Order (CCO) on the Completion Time of the Ditreskrimsus Polda Bali Building Construction,” Jurnal Ilmiah Teknik Unmas, vol. 4, no. 1, 2024.

[3] D. Fardila, M. S. Afandy, and E. Kurniati, “Analysis of Factors Causing Contract Change Order and Its Effect on the Implementation of Road and Bridge Construction Projects,” Jurnal Rekayasa Sipil, vol. 17, no. 3, 2023.

[4] A. Maulana, “Factors Causing Contract Change Order (CCO) and Its Effect on the Implementation of Dam Construction Projects,” Jurnal Infrastruktur, vol. 2, no. 2, 2016.

[5] I. A. R. Widhiawati, A. A. Wiranata, and I. P. Y. Wirawan, “Factors Causing Change Order in Building Construction Projects,” Jurnal Ilmiah Teknik Sipil, vol. 20, no. 1, 2016.

[6] J. C. Lela, F. J. Manoppo, and C. J. Supit, “Analysis of the Causes and Effects of Contract Change Order on Contractor Performance in Construction Projects in South Minahasa Regency,” Jurnal Ilmiah Media Engineering, vol. 12, no. 1, 2022.

[7] A. Murtopo, A. Nugroho, and M. A. Budihardjo, “A Study of Contract Change Order (CCO) in the Construction of the Integrated Laboratory Building, Universitas Tidar,” 2022.

[8] B. P. Nusantara and Sutardi, “Evaluation of Contract Change Order as a Solution to Contract Scope Change Problems,” 2023.

[9] B. Rinaldi, P. A. P. Suwandi, and A. Kristiawan, “Analysis of the Effect of Change Order on Implementation Time and Construction Labor Cost in the Construction of Unimus Joint Lecture Building III,” International Journal of Sustainable Building, Infrastructure and Environment (IJOSBIE), vol. 6, no. 1, 2025.

[10] Sugiyono, Qualitative, Quantitative, and R&D Research Methods. Bandung, Indonesia: Alfabeta, 2022.